Pilot Study – Design, Supply & Deliver of DfMA Manhole & Backdrops at the existing road intersection for Kwu Tung North New Development Area, Phase 1 – Contract No. ND2019/01

2021.10 - 2021.12

Period

Oct 21 – Dec 21

Description

This pilot study covers site formation works for the Kwu Tung North New Development, focusing on the construction of road and associated road drainage system. The works involve design, supply, delivery and site assembly of one special manhole with a footprint of 4500 x 5500 (mm²) x 5600 mm (H) with two backdrops within 3 months, demonstrating the DfMA approach for over 50 similar manholes required in the full project.

Client

Richwell Engineering Limited